Project Description
Located in Honduran territory on the CA-11 international highway, slope stabilization was required through the use of active anchors in addition to shotcrete and sub-horizontal drains.
Solution
The solutions provided in this project were necessary to stabilize the slopes of the road section due to a geological fault in the area.
Client:
Consorcio Copán
Country:
Honduras
Start Date:
Febrero 2020
End Date:
Junio 2021
Amounts of Work:
1,105 m2 of shotcrete.
3,694 lm of active anchors.
188 u of subhorizontal drains.
![](https://www.rodiosbo.com/wp-content/uploads/sites/10/2022/06/El-Florido-1-scaled.jpg)
![](https://www.rodiosbo.com/wp-content/uploads/sites/10/2022/06/El-Florido-2-scaled.jpg)
![](https://www.rodiosbo.com/wp-content/uploads/sites/10/2022/06/El-Florido-3-1-scaled.jpg)
![](https://www.rodiosbo.com/wp-content/uploads/sites/10/2022/06/El-Florido-4-scaled.jpg)
Related Techniques
Proyectos Relacionados
![DO YOU HAVE A PROJECT Rodio Swissboring - Trabaja con nosotros](https://www.rodiosbo.com/wp-content/uploads/sites/10/2020/12/DO-YOU-HAVE-A-PROJECT.jpg)
![DO YOU HAVE A PROJECT Rodio Swissboring - Trabaja con nosotros](https://www.rodiosbo.com/wp-content/uploads/sites/10/2020/12/DO-YOU-HAVE-A-PROJECT.jpg)